H.R. 2880 · 115th Congress
Promoting Closed-Loop Pumped Storage Hydropower Act
Key: what the circles and colors mean
Each circle is a bill. The ring fills as it moves through Congress:
Under the number: the Yea · Nay count of its final (or latest) recorded vote. On a member's page, the small badge is how that member voted: Y Yea / Aye, N Nay / No, P Present, – Not voting.
Gold and violet are only for Yea and Nay; they never mean a party. A member's party is the letter on their photo.
Passed the House without a recorded vote, then expired. It passed by voice vote or unanimous consent, which don't record how each member voted, but didn't become law before the 115th Congress ended.
No cosponsors.
- House Introduced Jun 12, 2017
- House Passed Dec 12, 2017
In establishing the expedited process, FERC shall convene an interagency task force with appropriate federal and state agencies and Indian tribes to coordinate the regulatory process associated with the authorizations required to construct and operate closed-loop pumped storage projects.
What it does: CRS summary · Passed House amended · Dec 12, 2017
Promoting Closed-Loop Pumped Storage Hydropower Act
(Sec.2)This bill amends the Federal Power Act to authorize the Federal Energy Regulatory Commission (FERC) to establish an expedited licensing process for issuing and amending licenses and preliminary permits for closed-loop pumped storage projects (in which the upper and lower reservoirs do not impound or directly withdraw water from navigable waters, or that are not continuously connected to a naturally flowing water feature).
In establishing the expedited process, FERC shall convene an interagency task force with appropriate federal and state agencies and Indian tribes to coordinate the regulatory process associated with the authorizations required to construct and operate closed-loop pumped storage projects.
FERC must assess the safety of existing dams and other structures related to the project before issuing any license for a closed-loop storage project.
FERC must hold a workshop to explore potential opportunities for development of storage projects at abandoned mine sites.
FERC must also establish criteria that a project shall meet to qualify as a closed-loop pumped storage under this bill, including requiring that the project cause little to no change to existing surface and groundwater flows and uses and that the project is unlikely to adversely affect species listed as threatened or endangered under the Endangered Species Act of 1973.
(Sec.3)Licensees are not required to pay an annual charge for administrative expenses until construction commences.
Written by the nonpartisan Congressional Research Service. All summary versions on Congress.gov
About this bill and sources
Official title: Promoting Closed-Loop Pumped Storage Hydropower Act
Latest action (Dec 13, 2017): Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.
Policy area: Energy · Origin: House · Introduced: Jun 12, 2017
Official page on Congress.gov · Bill text (GovInfo) · Status record (XML)
- House Introduced Jun 12, 2017
- House Passed Dec 12, 2017
No recorded floor vote found.