S. 1972 · 110th Congress

A bill to amend the Federal Power Act to modify a provision relating to the siting of interstate electric…

Full title

A bill to amend the Federal Power Act to modify a provision relating to the siting of interstate electric transmission.

Key: what the circles and colors mean

Each circle is a bill. The ring fills as it moves through Congress:

IntroducedPassed one chamberPassed both chambersBecame law (gold)Resolution agreed to (full, dark)Failed or vetoed (gray)

Under the number: the Yea · Nay count of its final (or latest) recorded vote. On a member's page, the small badge is how that member voted: Y Yea / Aye, N Nay / No, P Present, – Not voting.

Gold and violet are only for Yea and Nay; they never mean a party. A member's party is the letter on their photo.

Never voted on. It didn't reach a floor vote before the 110th Congress ended, so it expired. A bill has to be introduced again to be considered in a new Congress.

1 cosponsor · 1 D

1 signed on when it was introduced; the rest joined later. Cosponsors who withdrew aren't shown.

Amends the Federal Power Act to authorize the Federal Energy Regulatory Commission (FERC) to issue a construction permit for siting an interstate electric transmission facility if it finds that an authorized state entity has: (1) approved the siting of the proposed facility; or (2) unreasonably withheld a determination, or delayed making a determination,…

What it does: CRS summary · Introduced in Senate · Aug 2, 2007

Amends the Federal Power Act to authorize the Federal Energy Regulatory Commission (FERC) to issue a construction permit for siting an interstate electric transmission facility if it finds that an authorized state entity has: (1) approved the siting of the proposed facility; or (2) unreasonably withheld a determination, or delayed making a determination, for a period of at least two years after the date on which the permit application was filed.

Repeals provisions governing: (1) rights-of-way; and (2) compensation for acquisition of rights-of-way.

Prohibits FERC from issuing a permit if a state entity has denied a permit application for the same project during the two-year period beginning on the date the permit application is submitted to the entity.

Written by the nonpartisan Congressional Research Service. All summary versions on Congress.gov

About this bill and sources

Official title: A bill to amend the Federal Power Act to modify a provision relating to the siting of interstate electric transmission.

Latest action (Aug 2, 2007): Read twice and referred to the Committee on Energy and Natural Resources.

Policy area: Energy · Origin: Senate · Introduced: Aug 2, 2007

Official page on Congress.gov · Bill text (GovInfo) · Status record (XML)

No recorded floor vote found.